|
Oil and Gas Update Overview
The following is a brief synopsis of the current existing
or proposed oil and gas projects in Santa Barbara County, by
geographic area. Clicking on the highlighted
project names will provide more detailed information on the projects
themselves, as well as the current status of each proposal.
Carpinteria
There are currently two very important oil and
gas projects being proposed in the Carpinteria area, as well
as an abandonment project, as follows:
The Paredon Project is
a proposal by Venoco to conduct directional (extended reach)
drilling from an onshore operations site located at Venoco’s
existing Carpinteria Oil and Gas Processing Facility (CPF),
within the City of Carpinteria.
The Carone Petroleum Company proposes to
develop State Oil and Gas Leases 4000, 7911 and 3133 from a
federal platform, Platform Hogan, installed in 1967, and send
the oil to the La Conchita onshore facility via offshore pipeline.
The abandonment project involves the Chevron
Debris/Shell Mounds, left behind after the four “H” Platforms
were removed from the Santa Barbara Channel in 1996. Conditions
on the State Lands and Coastal Commissions’ permits
require that the area beneath the platforms be restored to
a natural condition and be “trawlable”. The
debris mounds have prevented Chevron from meeting this requirement.
Goleta
There are currently three imminent projects
in Goleta, clustered in the Ellwood area, all being proposed
by Venoco, Inc.:
Venoco has applied to the State Lands Commission to extend
the Ellwood Marine Terminal Lease until 2013. The
original lease was issued by the State Lands Commission in
1983, with the possibility of two 10 year extensions. Since
an application for an extension was not submitted in 1993,
the lease has been operating on a month to month basis since
that time. Official renewal will provide the SLC with
an opportunity to examine alternative modes of transportation,
as well as up-to-date safety and environmental standards on
this existing operation.
Venoco has applied to the State Lands Commission and the City
of Goleta to recommence operations on Lease
421, originally
leased in 1949. Production from two wells on two small
piers directly in the surf zone ceased in 1994, due to a break
in the pipeline that took the oil directly to the Ellwood Marine
Terminal. In 2000, Well #1 developed a leak and emergency
permits were issued to lay a 2” line from the well to
the Ellwood Onshore Facility (EOF) to relieve pressure and
stop the leak. Venoco is now proposing to recommission both
wells and process the oil from the piers.
Venoco’s application for Ellwood Full Field
Development, to the State Lands Commission, the
County of Santa Barbara and the City of Goleta, involves
a lease boundary extension into former State Leases 308 and
309, now part of the State Oil and Gas Sanctuary, processing
at the Ellwood Onshore Facility, abandoning the Ellwood Marine
Terminal and transporting all oil from Platform Holly by
pipeline. A multitude of issues are raised by this
proposal, involving both the potential environmental impacts
and legal requirements related to the 1991 agreement in which
ARCO Oil and Gas gave up its rights to drill into this same
area in exchange for additional drilling rights in Long Beach.
Lompoc
Plains Exploration and Development has submitted the Tranquillon
Ridge II application to the State Lands Commission
and the County of Santa Barbara to drill 22-30 new oil and
gas wells from Platform Irene (in federal waters) into a
new State tidelands oil and gas lease, using extended reach
technology. The oil would be sent to shore via pipeline
and processed at the Torch Oil and Gas Facility.
Currently, one well (A-28) on Platform
Irene has been drilled up to the state tidelands boundary. In January of 2000,
Nuevo Energy/Torch Operating Co. submitted essentially the
same application for Tranquillon Ridge I. In October
of 2002, the County Board of Supervisors denied that project. As
a result, the request for a proposed new lease was never heard
by the State Lands Commission.
Countywide
There are currently 37 existing federal leases (were
36) off the coast of Santa Barbara, Ventura and San Luis Obispo
counties which the Minerals Management Service (MMS) extended
in 1999. Due to the age of these leases, none of
them were reviewed by the California Coastal Commission when
they were leased or extended.
A series of lawsuits were brought challenging
the failure of the MMS to conduct environmental review (and
later inadequate environmental review) and failure to allow
the State to review the leases. In June, 2001, the
federal district court directed the MMS to conduct environmental
review and submit the lease extensions to the California
Coastal Commission. And later ruled that that MMS could not
grant the suspensions until the agency completed full environmental
review, including review of future exploration and development
activities. The federal government then filed an appeal to
the Ninth Circuit Court of Appeals.
Abbreviations and Acronyms
For a list explaining some commonly used oil
and gas related acronyms and abbreviations, click
here. (PDF)

back
to top
Paredon Project
Project Description: Venoco
proposes to conduct extended reach (directional) drilling
from its existing onshore operations/oil and gas processing
facility site (zoned CD-Coastal Dependent), located south
of Highway 101, off of Dump Road in the City of Carpinteria. The drilling site is adjacent
to Carpinteria City Hall and within 1000 feet of 1000 people
living in the Arbol Verde and Concha Loma Neighborhoods, as
well as the San Roque and Granada Mobile Home Parks. In
addition, Carpinteria Middle School, with over 400 students,
is less than one mile away. The recently preserved Carpinteria
Bluffs is just down coast and the seal haul out area is on
the beach immediately below the drilling site, both environmentally
sensitive.
The project, which would augment the existing facilities by
installing new facilities and modifying others, can be grouped
into four distinct components:
- Onshore drilling and production of onshore and offshore
oil and gas resources (for approximately 4 years)
- Onshore processing and distribution of oil
- Onshore processing of produced water
- Onshore processing and distribution of natural gas
The new proposed facilities would be integrated with existing
onshore oil and gas processing, pipeline transportation and
storage facilities. While the physical footprint of the existing
facility would not increase, approval of a 175 foot tall electric
drilling rig would significantly change the existing uses and
appearance of the area, resulting in new and increased impacts
to the local community and coastal visitors.
If the exploration well indicates that the development would
be commercially viable, permanent drilling facilities would
be installed and the necessary modifications to the existing
facilities made. A number of electrical submersible pumps would
also be installed (placed down a production well) to pump oil
and gas to the surface.
Background: On January
23, 2002, and again on November 21, 2002, the State Lands
Commission found Venoco’s
application incomplete. In February, 2003, the City of Carpinteria
notified the SLC that it will retain lead agency status under
CEQA and signed a 5 year contract with the County, for Energy
Division services on the project. It appears that additions
will need to be made to Carpinteria’s zoning ordinance
relating to offshore oil since they do not currently exist. On
August 13 and 30, 2004, Venoco submitted applications to the
SLC and the City of Carpinteria, respectively. On September
10th and 30th SLC and the City, respectively, found the applications
incomplete. SLC then received a revised application
and found it complete on March 4th, 2005. Carpinteria
also received a revised application, but found it incomplete
on March 2nd. On October 12th, 2005 Carpinteria
deemed Venoco’s resubmitted application complete and
on March 27, City Council authorized Marine Research Specialists
(MRS) as the EIR consultant for the project. A public
information workshop was held on April 18th and a scoping hearing
on June 13th.
Status: The Draft EIR was released
on June 11, 2007, a workshop held on June 26th, and a public
comment hearing on July 30th with an August 9th deadline
for written comments. It is expected that the FEIR
will be released in late 2007-early 2008.

back
to top
Carone Petroleum Company
Project Description: Carone Petroleum
Company proposes to develop State Oil and Gas Leases 4000,
7911 and 3133 within the Carpinteria Field. Carone specifically
proposes to to drill up to 25 new production or injection wells
from Outer Continental Shelf (OCS) Platform Hogan, constructed
in 1967. Oil and gas production from the State Leases
would be commingled on Platform Hogan with existing production
from the Federal lease and sent via existing pipelines to the
La Conchita Facility. After processing, gas and oil are
sold to The Gas Company and other third parties at the La Conchita
sales meters, and shipped via existing pipelines.
Background: The Draft
EIR is currently on hold. The API Level 3 structural survey
of Platform Hogan was completed and, on October 24th, 2003,
Carone requested a one year extension to complete the upgrades
to Platform Hogan required by MMS. MRS, the consultant, submitted
the Administrative DEIR on the proposed project to SLC staff
in February, 2005. Prior to publication of the public
Draft, the MMS contacted both SLC staff and the applicant
requesting that the document be issued as a joint NEPA/CEQA
document.
Status: SLC staff is working with MMS to revise
the document to meet NEPA requirements. SLC staff has also
decided to include the information from the engineering report
to determine any necessary modifications to accommodate the large
electric rig to implement the proposed project. Staff received
and reviewed the engineering report, which it found to be incomplete. Comments
were submitted to Carone in late July and SLC received the revised
report at the end of October. SLC Staff has indicated to
Carone that additional changes are still needed to the engineering
report which will dictate what changes will need to be made to
Platform Hogan. There is no estimated date for the release
of the Draft EIR.

back
to top
Chevron Debris/Shell Mounds
Project Description: The
four “H” Platforms
were removed from the Santa Barbara Channel in 1996, leaving
behind four debris mounds, each approximately 200+ feet
long and 30 feet high. The SLC commissioned a study in 2001
that concluded that there were contaminants in the mounds and
that a variety of methods were available to remove the mounds
without the use of explosives. In 2001, Chevron applied
to the SLC for a project (to be determined) on the disposition
of the mounds.
The mounds are composed of 3 layers, the
top layer made up of shell hash (mussel, clam and barnacle
shells), the second layer of drill cuttings and the bottom
layer of sea floor sediments (clay). The middle layer
was found to contain contaminants from the drill muds and
cuttings which were dumped from the platforms.
Background: Conditions on the State
Lands and Coastal Commissions’permits required that the
area beneath the platforms be restored to a natural condition
and be “trawlable”. Due to the size of the
mounds, this requirement cannot currently be met. Shortly after
the EIR preparation began, it was determined that a bioassay
study should be done to determine whether or not contaminants
were leaching into the water column. On June 26th, the
SLC held a Stakeholder Briefing on the results of the Bioassay
Mussel Study.
The Draft EIR was released on December
15th, with a 60-day review period. Staff is in the process of responding
to comments on the DEIR, including a Habitat Equivalency Analysis
(HEA) submitted by Chevron. These types of analyses are
used, as part of a Natural Resource Damage Assessment, to determine
the most environmentally beneficial course of action following
an environmentally damaging event, such as an oil spill. Chevron
indicates that this analysis shows that creation of a reef
and offsite mitigation at Carpinteria Marsh is the most environmentally
beneficial alternative. SLC is reviewing, and deciding how
to respond to Chevron’s submittal. The environmental
groups and PCFFA continue to support removal of the mounds
as the preferred long-term solution.
Status: SLC has received an application, but the
pilot project at Platform Heidi is listed as one of three alternatives,
along with the reef and capping. The “proposed” project
is to leave the mounds in place and provide for mitigation at
Carpinteria Marsh. Chevron is using the HEA as justification
for this project.

back
to top
Ellwood Marine Terminal Lease Extension
Project Description: Venoco
has applied to the State Lands Commission for an extension
to its marine terminal lease until 2013. The marine
terminal consists of
Background: Venoco’s original
lease for the Ellwood Marine Terminal was issued by the State
Lands Commission in 1983, with the possibility of two 10 year
extensions. Since an application for an extension was
not submitted in 1993, the lease has been operating on a month
to month basis. Official renewal is critical because
it will allow the SLC to apply up-to-date safety and environmental
standards.
Venoco’s application to the SLC for a 10-year lease extension
to its Ellwood Marine Terminal was found complete on July 2,
2003. On August 19, 2003, the SLC authorized staff to negotiate
a contract for CEQA review of the project. Scoping
hearings were held on August 3, 2004. SLC
staff received the Administrative DEIR from the consultant,
Marine Research Specialists, in late August, 2005 and provided
extensive comments on it. The DEIR was issued in late
July, 2006, and a public hearing was held on August 30th.
Status: The Final EIR was released in August. A State Lands Commission public hearing set for October 30th in San Diego has been postponed. A new hearing date has not yet been set.

back
to top
State Lease 421 Recommissioning
Project Description: Venoco
has submitted an application to return State Lease PRC-421
to production. The
project includes the removal of old production equipment from
oil piers 421-1 and 421-2 (which are California’s last
remaining surfzone oil piers); repairs to the access road,
rock rip-rap wall, and caisson at the end of pier 421-1; installation
of a drilling rig and new oil separation and processing equipment
on pier 421-2; and reactivation of the oil well on pier 421-2
with a capacity to produce up to 700 BPD (111 m3/d). The
oil would be pumped to Line 96 through an existing pipeline
and then to the EMT. The existing pipeline between Line 96
and the 421-1 pier would be upgraded.
Background: Originally
leased in 1949, renewed in 1959, production from two wells
from two small piers ceased in 1994, due to a break in the
pipeline that took the oil directly to the marine terminal. In 2000, Well #1 developed a
leak and emergency permits were issued to lay a 2” line
from the well to the Ellwood onshore facility (EOF) to relieve
pressure and stop the leak. Secondary emergency permits
were issued in March of 2001 to complete the stabilization
of both wells and to repair the access road and piers. Regular
permits were then issued for the emergency work in late 2001.
In May, 2003, Venoco sent a letter to
the City of Goleta asserting its vested right to recommission
the two wells, with the oil continuing to go directly to
the marine terminal. The
letter then suggested that there might be a better way to process
the oil (probably at the OEF). Venoco has indicated that
it does not believe a permit is needed from the SLC to recommission,
however SLC staff says that an SLC permit IS required, pursuant
to SLC Reg. #2137. On May 17, the City of Goleta sent a letter
to the SLC stating opposition to restoration of oil and gas activities
on Lease 421. On July 15th, SLC staff
wrote to Venoco directing the company to repair the seawall
protecting Caisson #1, but indicating that such an action would
have no effect on any discretionary action on Venoco’s
application to return Lease 421 to production. Venoco
submitted an application to the SLC on May 19, 2004 which was
found incomplete on June 19, 2004. On December 14, 2004,
SLC received a response to its incomplete letter, but did not
issue an incomplete letter before January 14th, thereby (defacto)
allowing the application to become complete. In June, 2005,
SLC selected a consultant for the EIR and a scoping hearing
was held on June 23, 2005 in Goleta.
Status: The DEIR was released in early September, 2007, with a workshop/public hearing set for October 16th in Goleta. The deadline for written comments is 4:00pm on November 16th.

back
to top
Ellwood Full Field Development-Lease Boundary Adjustment
Project Description: Venoco
is proposing to fully develop the Ellwood Offshore field
through the use of a lease boundary extension, processing
the oil at the Ellwood Onshore Facility, abandoning the Ellwood
Marine Terminal and transporting all oil from Platform Holly
by pipeline. The
project would include:
- Construction of a new 10-inch (25-cm) diameter, 10-mile
(16-km) onshore pipeline to transport
oil from the Ellwood Onshore Facility (EOF) to the Plains
All American Pipeline system at Las Flores Canyon;
- Decommissioning and abandonment of
the EMT and Line 96. Restoration
of the EMT site and discontinuation of marine transportation
via barge;
- Adjustment of the existing PRC 3242.1 lease boundary to
encompass the eastward section of the South Ellwood Field;
- Drilling of up to 40 new wells on both the existing leases
and the proposed project area;
- Replacement of the existing crane on Platform Holly;
- Replacement of the existing 2-inch (5-cm) utility pipeline
and subsea power cable between the EOF and Platform Holly;
and
- Various improvements at the EOF, including
a new power generation plant.
Oil production is expected to peak at
12,600 BPD (2,003 m3/day) and gas production at 20 MMSCFD
(566,337 m3/day) after five years.
Background: A number
of projects have been proposed for the full development of
the Ellwood Field, the most recent being the “Clearview” project which
proposed the use of extended reach drilling from onshore to
leases 308 and 309 which were quitclaimed to the State by ARCO
in exchange for additional drilling rights in the Long Beach
area. Clearview was abandoned by Mobil when the UCSB
Chancellor decided not to grant a lease to Mobil for the drill
site. Venoco has since explored a number of scenarios
to develop the balance of the Ellwood Field from Platform Holly
and has submitted a variety of applications, but none of them
were found complete. On August 1, 2005, Venoco submitted applications
to the State Lands Commission, the County of Santa Barbara
and the City of Goleta (as required by AB 16, former Assemblymember
Hannah-Beth’s pipeline bill). All three entities
found their respective applications incomplete on August 31st. The
resubmitted applications were found complete by all three entities
on March 31, 2006. SLC is lead agency, however, a City/County/SLC
Joint Review Panel (JRP) was formed. The
Notice of Preparation was issued on June 28th and a scoping
hearing held on July 24, 2006. MRS has been selected
as the consultant.
Status: It is expected that the Draft EIR will be released in late 2007/early 2008.

back
to top
Tranquillon Ridge II
Project Description: Plains
Exploration and Development is requesting approval to drill
22-30 new oil and gas wells from Platform Irene (in federal
waters) into a new State tidelands oil and gas lease, using
extended reach technology. Currently,
one well (A-28) on Platform Irene has been drilled up to the
state tidelands boundary. The project would extend the
life of the onshore Lompoc Oil and Gas processing facility
by up to 25 years.
Sunset Exploration, with partners Exxon/Mobil,
has also proposed an onshore alternative to drill and process
the oil from Vandenberg AFB. The County will be lead
agency on both projects.
Background: In
January of 2000, Nuevo Energy/Torch Operating Co. submitted
an application for Tranquillon Ridge I, essentially the same
project as Tranquillon Ridge II. On October 22, 2002, the County Board of Supervisors
denied that project. As a result, the request for a proposed
new lease was never heard by the State Lands Commission, however
SLC staff did determine that state oil deposits were “being
drained” by means of producing wells on adjacent federal
lands, a necessary finding for any new oil and gas leases to
be issued within the Calif. Coastal Sanctuary (PRC 6244).
Status: Nuevo Energy was purchased by
Plains Exploration and Development in September and in December,
2004, submitted an application to the County which was found
incomplete. Plains’ application
was resubmitted and found complete on March 10, 2005. On
May 19th, the SLC also found the application complete. A
Joint Review Panel (SBC/SLC/CCC) was created and a consultant
hired. Expected release of the Plains project DEIR is
November, 2006. The Plains project DEIR was released
the first week in November, 2006. Workshops/hearings
were held November 15th and December 11th, and comments were
due January 16, 2007.
Status: It is expected that the Final EIR will be released in November, 2007.
Sunset Exploration, with partners Exxon/Mobil,
has also proposed an onshore alternative to drill and process
the oil from Vandenberg AFB. Sunset resubmitted its application in January, 2007,
but it was found incomplete. The County will be lead
agency on both projects.

back
to top
Countywide
Project Description: The
Minerals Management extended 37 (was 36) existing federal
leases off the coast of Santa Barbara, Ventura and San Luis
Obispo counties in 1999. Due
to the age of these leases, none of them were reviewed
by the California Coastal Commission when they were leased.
Background: EDC represented eight environmental
groups (Get Oil Out Sierra Club, Santa Barbara Channelkeeper,
Defenders of Wildlife, The Otter Project, Surfrider Foundation
and CPA) in litigation challenging the failure of the MMS to
conduct environmental review and allow the State to review
the leases. In June, 2001, the federal district court directed
the MMS to conduct environmental review and submit the lease
extensions to the California Coastal Commission. This decision
was upheld by the court of appeals in December, 2002. On December
9, 2003, the US District Court directed the MMS to submit a
schedule complying with the judgment requiring State review
of these oil and gas leases. On February 26, 2004 the Court
ordered MMS to submit a report by May 27 with a schedule for
compliance with NEPA and the Coastal Zone Management Act. On
April 20, 2004 the oil companies submitted their updated requests
for suspensions to MMS. The requests included schedules
to commence exploratory and production drilling in the next
2-3 years. No activities are currently being proposed on 12
of the 37 leases, raising the possibility that these leases
should be expired without compensation. The proposed schedule
submitted by the MMS for NEPA compliance (environmental review)
and CZMA compliance (federal consistency review) did not provide
for environmental review of all potential activities on the
leases. On June 28, the court approved the NEPA/CZMA
compliance schedule in spite of this inadequacy.
On November 17, 2004, MMS released the
Draft Environmental Assessments (not Environmental Impact
Statements) for the lease extensions with comments due on
December 16. Numerous
groups commented, requesting environmental review of all impacts
that could result from future exploration, development and
production activities on the leases, as well as an evaluation
of a full range of alternatives (inc. conservation, efficiency
and clean renewable energy sources). Nonetheless, on
February 11, 2005, MMS released the final Environmental Assessments
and Findings of No Significant Impact (FONSI).
On March 8, 2005, EDC and NRDC, representing
10 environmental groups, filed a lawsuit challenging MMS’s determination
that extending the (now 37) leases would not result in any
negative environmental effects. Pursuant to the 2002
court of appeals ruling, MMS submitted federal consistency
determinations on the federal oil and gas lease suspensions
to the Coastal Commission in April. Environmental groups
filed their opening brief on June 23. On
August 11th, the Coastal Commission objected to the federal
consistency determinations on all of the leases. MMS
did not even send a representative to the hearing. The
next day, Judge Claudia Wilken ruled that that MMS could not
grant the suspensions until the agency completed full environmental
review, including review of future exploration and development
activities.
Status: The
federal government filed an appeal to the Ninth Circuit
Court of Appeals. In
the meantime, a federal court of claims ruled that the application
of the Coastal Zone Management Act (as amended in 1990 to
expand the right of coastal states to review federal activities)
to these leases constituted a breach of contract and awarded
restitution to the lessees in the amount of $1.1 billion. If
the government pays restitution, the leases will be extinguished. We
are waiting to see if the federal government will appeal
this ruling. Our case has been stayed pending resolution
of the Amber Resources case.
back
to top
|